Lags and Leads Menu Group on the S2 // Logic Tab

Use the options in this menu group to display relationship links that are carrying positive and negative lags and leads.

Field Description
Lags This option displays only relationships with lags. This is often used to represent non-working time between activities. For example, time for concrete to cure.
Leads This option displays only relationships with leads. A lead is a negative lag. This is often used to adjust the successor start/end date relative to the logic link applied. It can result in the successor starting before the start of the predecessor.